CAMBRIDGE
VIADUCT

 
 
 
 

PROBLEM:

 

In 2019, CSC was contacted by SPS New England, Inc. to provide Carbon Fiber Reinforcement to the arches and floor beams supporting the East Cambridge Viaduct bridge to supply additional load capacity to the existing structure. The work consisted of surface preparing the structures, CFRP installation, anchors installation, and acrylic painting.

 
 

MATERIALS:

 

CFRP: Tyfo® SCH-41H, Tyfo® CWEB-41, Tyfo® SCH-41-2X

Primer: Tyfo® S Epoxy & Thickened Tyfo® S Epoxy

Anchors: 1/4" Dia. Tyfo® SCH Composite Anchors

Cab-O-Sil (Epoxy thickening agent)

 

PICTURED: The structural health of the bridge before an rehabilitation work had started on the structure.

PICTURED: The structural health of the bridge before an rehabilitation work had started on the structure.

 
 

SURFACE
PREP:

 

The surfaces on the floor beams and arches of the bridge were fully prepared, providing a minimum of CSP-2 surface roughness. The surface preparation cleared all the laitance, dust, grime, etc. located on the surfaces to properly install the FRP material. The following photos demonstrate the cleaned surface ready for the application of carbon fiber material.

 

ABOVE: Outside Arch Surface Preparation.

 

ABOVE: Floor Beam Surface Preparation

 

ABOVE: Inside Arch Surface Preparation

 
 

SOLUTION:

After completing all required surface preparation, a prime coat of thickened Tyfo® S Epoxy was applied to the substrate to fill all minor imperfections, deflection, voids, etc., in the substrate prior to installation of the saturated fabric. The TYFO CFRP material fabric was hand saturated to ensure impregnation of all fabric with Tyfo® S Epoxy. All air bubbles were worked out of the system. System was leveled set and sealed using an additional coat of thickened Tyfo® S Epoxy.

The carbon fiber was then sand sprayed to match the texture of the rest of the bridge. After the CFRP and the Tyfo® S Epoxy were properly cured, a layer of acrylic painting was applied to every arch and floor beam installed with CFRP. The following photos show the completed CFRP application on the arches and floor beams along with the acrylic paint coating.

 

ABOVE: Finished Floor Beam CFRP Installation

 

ABOVE: Floor Beam CFRP Installation

 

ABOVE: Inside Arch CFRP InstallatioN

 

ABOVE: Finished Inside Arch CFRP Installation

 

ABOVE: Floor Beam Acrylic Coating

 

ABOVE: Arch Acrylic Coating

 
 
 
 

CONCLUSION:

 

After completing the CFRP installation, a thorough inspection of the work was done, recording the materials used, and a sample panel (Appendix 2), for future tensile testing (by others, if required) was cast in accordance with ASTM-D-/D3039, revision 12/2002. An adhesion test was performed on multiple locations by a qualified CSC employee following ASTM criteria. CSC walked the project with SPS New England, Inc. on-site Superintendent who was notified of pending demobilization and communicated no issues found. All CFRP areas were broom cleaned and CSC demobilized on 12/17/2021.

RELATED CASE STUDIES AND ARTICLES:

130 IRVING PLACE

A full rehabilitation project consisting of a multi level concrete slab structure being renovated for a client located in Woodmere NY.

CONCRETE REPAIR

To properly fix concrete, you have to treat all aspects of the disrepair. That means making sure that your concrete is in the best shape possible.

The Four Most Common Types of Concrete Damage

Learn about the different types of damage that can happen to your concrete structure!